Project Overview
The Health Professions Building Addition consists of 62,500 square feet which includes an auditorium, clinical suite, simulation suite, anatomy labs, discussion rooms, learning commons, and facility and administrative offices.
The project is targeting certification under LEED-NC (New Construction
Total Project Budget: $19,430,000
Project Schedule
Design Complete
February 2010
Construction Bids Due
April 2010
Construction Start
May 2010
Construction Substantially Complete
September 2011
Owner Occupancy
January 2012
Project Status
Metal roof panels to complete in June.
Electrical shutdown required for the emergency circuit breaker installation. Scheduled for the first week of June.
Second Floor drywall and finish to complete in June.
Carls Center waiting area in Schematic Design.
Restroom wall tile complete.
Upcoming Milestones
Restroom wall tile complete.
Lighting fixture installation on going.
Ceiling grid to complete in June.
Interior wood ceiling to complete in June.
Mechanical air handling unit to start in June. Millwork to complete in July.
Flooring to complete in July.
Furniture order to complete in August.