Complete? |
Year |
Month |
Event |
X |
2003 |
Sept. |
Provost
forms a Self-Study Steering Committee |
X |
. |
Oct. |
Steering
Committee forms subcommittees,
one for each criterion, and issues
charge |
X |
. |
Nov. – Dec. |
Subcommittees
organize themselves and study new
accreditation criteria |
X |
2004 |
Jan. – Apr. |
Subcommittees
identify and gather data relevant
to their criteria
|
X |
. |
March |
Steering
Committee attends HLC annual meeting
and sessions on what is expected |
X |
. |
Apr. – May |
Subcommittees
organize and summarize the information
gathered. |
X |
. |
Apr. – July |
Steering
Committee and subcommittees establish
how to evaluate CMU’s performance
relative to its mission statement & the
accreditation criteria |
X |
. |
May |
Writer
for self-study identified and contracted |
X |
. |
June |
Writer
completes preliminary draft of
the introductory background chapter |
X |
|
July |
Writer completes first preliminary
draft of chapter dealing with criterion
I - Mission & Integrity |
X |
. |
July – Nov. |
Skeletons
of the chapters dealing with criteria
II - V are prepared |
X |
. |
Oct.– Dec. |
Initial
evaluations carried out; results
given to writer as they become
available. |
X |
. |
Sept. – Dec.
|
Writer
completes preliminary drafts of
the chapters dealing with the five
criteria
|
X |
. |
Sept. – Dec. |
Committees
and subcommittees react to drafts
|
. |
2005 |
Jan.
- Feb. |
Writer
finalizes drafts |
X |
.. |
Jan. – March |
Drafts
of the Self-Study chapters circulated
to campus community for reaction. |
X |
. |
Feb. – March |
Steering
Committee reacts to drafts. |
X
|
. |
March
- Apr. |
Drafts of the Self-Study chapters circulated to campus
community for reaction.
|
X |
. |
March
- May |
Drafts revised in response to
reactions from campus community |
X |
. |
July 22 |
Final Draft of full Self-Study
Report completed and circulated for
comment |
| . X |
. |
Aug. 2 |
Issue call
for public comment |
|
X |
. |
Sep. 2 |
Electronic Version
of Self-Study Report sent to HLC |
|
X |
. |
Sep. 15 |
Printed version of Self-Study Report sent to site visitors |
|
X |
. |
Oct. 15 |
Virtual
reference room complete |
|
X |
. |
Oct. 15 |
Finalize
schedule and space for the visiting
evaluation team |
|
X |
. |
Oct. 31 - Nov. 2 |
Visit by