Summer 2018

Construction Hotline 989-774-6500

Construction is ongoing at the following locations:


    Central Avenue Construction of a gateway arch on Central Avenue and Broomfield continues through 8/22/18.
     
    Dow Science Hydro excavation work will occur 8/2/18 on the southwest corner of the building.  Sidewalks will remain open.
     
    East Complex Residence Halls
     
    Access control work on stairwell doors will conclude on 8/22/18.  Stairwell will be accessible.
     
    Field Hockey Field turf replacement will take place through 8/29/18 along the northeast side of the Field Hockey field.  The work area is contained.  The west half of Lot 61 will be barricaded for construction staging and traffic until 8/31/18.
     
    Grounds South Installation of new Fuel Tank will continue through 8/30/18.     
     
    Health Professions Building
     
    The Center for Integrated Health Studies construction site is established and the work area is fenced until the completion of project. Exterior access has been re-routed until the project is complete.   
     
    Temporary closure of the west entrance will occur 8/23 & 24/18.
     
    Lot 62 Additional exterior lighting work will occur near the SAC on Central Avenue through 9/30/18.  The sidewalk will remain open.
     
    Music Hall Classroom ADA security door hardware upgrades continues through 8/31/18.
     
    North Complex
     
    Access control work on stairwell doors will conclude 8/22/18.  Stairwell will be accessible.
     
    Rose Center Classroom ADA security door hardware upgrades continues through 8/31/18.
     
    Rose Center Gymnastic Locker Rooms 141C, J, K, L, M, N & O will be closed for renovations through 9/10/18


    Please see  SummerConstructionProgram.pptx for additional details.

    Critical Paths Map 2017-2018

    Plant Engineering and Planning Department at 989-774-6559 .