Health Professions Building Addition

Project Overview

The Health Professions Building Addition consists of 62,500 square feet which includes an auditorium, clinical suite, simulation suite, anatomy labs, discussion rooms, learning commons, and facility and administrative offices.

The project is targeting certification under LEED-NC (New Construction

Total Project Budget: $19,430,000

Project Schedule

Design Complete February 2010
Construction Bids Due April 2010
Construction Start May 2010
Construction Substantially Complete September 2011
Owner Occupancy January 2012

Project Status

Metal roof panels to complete in June.
Electrical shutdown required for the emergency circuit breaker installation. Scheduled for the first week of June.
Second Floor drywall and finish to complete in June.
Carls Center waiting area in Schematic Design.
Restroom wall tile complete.

Upcoming Milestones

Restroom wall tile complete.
Lighting fixture installation on going.
Ceiling grid to complete in June.
Interior wood ceiling to complete in June.
Mechanical air handling unit to start in June. Millwork to complete in July.
Flooring to complete in July.
Furniture order to complete in August.

Visual Information

 

 

CENTRAL MICHIGAN UNIVERSITY

1200 S. Franklin St • Mount Pleasant, Mich. 48859
Phone: 989-774-4000

CMU is an AA/EO institution, providing equal opportunity to all persons, including minorities, females, veterans, and individuals with disabilities. | CentralLink
Copyright Central Michigan University, Mount Pleasant, Mich. 48859 | Phone 989-774-4000 | Privacy Policy | Feedback | Full Site