Ronan Hall Renovation

Project Overview

This project will provide renovated open office, conference and classroom space to house departments that provide support services to the students of CMU.

The project is targeting certification under LEED – Commercial Interiors.

Total Project Budget: $3,625,000

Project Schedule

Program Complete March 2009
Schematic Design Complete May 2009
Design Development Complete July 2009
Construction Documents Complete January 2010
Project Bid February 2010
Construction Start July 2010
Construction Complete December 2010

Project Status

Construction started June 1, 2010.
Elevator decommissioning work is complete.
Domestic water environmental removal work is complete.
Domestic water system replacement work is complete.
Mechanical demolition system removal work is complete.
Masonry restoration work is complete.
Architectural, mechanical and electrical interior build-out is complete.
Campus utility exterior tie-in work is completed.
Campus utility interior tie-in work is completed.
Building commissioning work is completed.
Architectural, mechanical and electrical punch list work is in progress.

Upcoming Milestones

Construction punch list work continues.